UK grid connection intelligence

Know if a site can connect to the grid, and when, before you spend money on it.

We read Britain's national connection register and the planning and contract records around it, and tell you what they mean for your site: how long the wait is, who is ahead of you, and what could move your date. You get evidence you can put in front of a landowner, a board or an investment committee before anyone signs.

If a paid report does not answer your brief, you do not pay. Fixed fee, agreed before we start.

110 busiest sites. DarkerBrighter means a longer wait.Open map →
592 GW
waiting to connect, in 1,675 projects
6.7 years
average wait to the contracted date
75%
of waiting capacity is dated 2031 or later
4%
of waiting capacity is marked Gate 2, the firm tier

ConfirmedOur analysis of the NESO TEC Register, file of 23 November 2026. Transmission connections only. Waits are capacity-weighted.

Start here

Three ways in

Want to see the depth first? Read a sample screening report.

From the briefing

Three recent signals, and why they matter

A sample of the free weekly briefing. Every figure carries its source and a status tag.

Connections reform
31 Oct

On 25 September 2026 NESO asked Ofgem to move the Gate 2 Phase 1 offer deadline from 30 September to 31 October 2026. A further extension has been reported but we have not found it confirmed.

So what: firm offers are arriving later than planned, so dates built on them may slip.

ConfirmedNESO letter to Ofgem Reportedfurther extension

Balancing costs, Sept 2026
£541m

NESO's balancing costs for September 2026, of which about £390m was paying for grid constraints. NESO's own month-ahead forecast was £306m.

So what: most of that money pays for a shortage of network capacity, the same shortage that holds up new connections.

ConfirmedNESO BSUoS outturn

The queue, 23 Nov 2026
75%

That share of the capacity waiting to connect has a contracted date of 2031 or later. Gate 2 projects, by contrast, are mostly due by 2029.

So what: without a Gate 2 offer, plan on a long wait and check the date before you commit money.

ConfirmedOur analysis of the NESO TEC Register

Contact

Name a substation. We will send you its queue, free.

Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.

No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.

✓ Received. We will email you within one business day.

Or email info@benzene-group.com