Register changes
NESO republishes its whole connection register twice a week. We compare each file with the one before and list every project that joined, left, or moved its date. Latest comparison: the register of 23 November 2026 against 19 November 2026.
2 joined, 2 left, 2 connection dates moved (1 later, 1 earlier), 9 other changes.
| Project | Site | MW | Was | Now | Change |
|---|---|---|---|---|---|
| Glen Ullinish Wind FarmGlen Ullinish Wf Limited | Glen Ullinish 132/33kV Substation | 50 | 16 April 2028 | 25 November 2031 | +3.6 yrs |
| Lisa's Battery StoragePotencia Energy Limited | Mybster 3 132/33kV Substation | 47 | 31 October 2030 | 30 July 2028 | -2.3 yrs |
| Project | Site | Technology | MW | Contracted date | Gate |
|---|---|---|---|---|---|
| South Humber BankEp UK Power Development Ii Ltd | South Humber Bank 400kV Substation | CCGT (Combined Cycle Gas Turbine) | 0 | no date | No Gate shown |
| South Humber BankEp UK Power Development Ii Ltd | South Humber Bank 400kV Substation | CCGT (Combined Cycle Gas Turbine) | 35 | 30 October 2039 | Gate 1 |
| Project | Site | Technology | MW | Was contracted for |
|---|---|---|---|---|
| South Humber BankEp UK Power Development Ii Ltd | South Humber Bank 400kV Substation | CCGT (Combined Cycle Gas Turbine) | 35 | 30 October 2039 |
| Ochill BESSCarlton Power Limited | Ochill 132kV Substation | Energy Storage System | 50 | 18 August 2028 |
| Project | Site | What changed |
|---|---|---|
| Littlebrook BESSEcodev (South) Ltd | Littlebrook 132kV Substation | status Scoping to Awaiting Consents |
| Bilbo FarmLel Bilbo Solar Limited | Strichen 132/33kV GSP Substation | status Scoping to Consents Approved |
| Greenburn Mixed TechnologyReg Greenburn Limited | Greenburn Mixed Technology 132kV Substation | size 90.0 MW to 63.0 MW |
| Glen Ullinish Wind FarmGlen Ullinish Wf Limited | Glen Ullinish 132/33kV Substation | Gate not shown to 2 |
| Newarthill Energy ParkDalzell (Newarthill) Ltd | Newarthill Energy Park 275kV Substation | status Scoping to Awaiting Consents |
| Lisa's Battery StoragePotencia Energy Limited | Mybster 3 132/33kV Substation | Gate not shown to 2; status Awaiting Consents to Consents Approved |
| Templeton BESSTempleton Battery Storage Limited | Lyndhurst GSP | status Scoping to Consents Approved |
| Rogerton Cottage BESSDrax Bess Ek Limited | East Kilbride 275/33kV GSP | status Scoping to Consents Approved |
| Welbeck-Newark Solar Farm - PVDPSolarten Ltd | High Marnham 400kV Substation | Gate not shown to 1 |
1 joined, 3 left, 5 connection dates moved (5 later, 0 earlier), 12 other changes.
| Project | Site | MW | Was | Now | Change |
|---|---|---|---|---|---|
| Norwich YareAshgreen Energyfarm Limited | Norwich Main 400kV Substation | 50 | 18 December 2025 | 24 April 2027 | +1.3 yrs |
| Sellindge Grid Stability ServicesSellindge Grid Services Limited | Sellindge 400kV Substation | 0 | 11 August 2026 | 30 October 2027 | +1.2 yrs |
| Achany Extension Wind FarmSse Generation Limited | ACHANY EXTENSION WIND FARM 132/33KV Substation | 81 | 30 March 2028 | 26 March 2029 | +1.0 yrs |
| Spennymoor Greener Grid ParkSpennymoor Grid Solutions Limited | Spennymoor 400kV Substation | 0 | 29 October 2027 | 1 October 2028 | +0.9 yrs |
| Melksham (Tertiary)Melksham Calne Green Limited | Melksham 400kV Substation | 57 | 26 June 2026 | 31 December 2026 | +0.5 yrs |
| Project | Site | Technology | MW | Contracted date | Gate |
|---|---|---|---|---|---|
| Templeton BESSTempleton Battery Storage Limited | Lyndhurst GSP | Energy Storage System | 50 | 31 October 2028 | Gate 2 |
| Project | Site | Technology | MW | Was contracted for |
|---|---|---|---|---|
| Templeton BESSTempleton Battery Storage Limited | Lyndhurst 132/33kV | Energy Storage System | 30 | 31 October 2027 |
| Templeton BESSTempleton Battery Storage Limited | Lyndhurst 132/33kV | Energy Storage System | 20 | 31 October 2031 |
| Patford Bridge Farm548 UK Investment Holdings Limited | Patford Bridge 400kV Substation | Energy Storage System;PV Array (Photo Voltaic/solar) | 200 | 31 October 2033 |
| Project | Site | What changed |
|---|---|---|
| Littlebrook BESSEcodev (South) Ltd | Littlebrook 132kV Substation | Gate not shown to 2 |
| Spennymoor Greener Grid ParkSpennymoor Grid Solutions Limited | Spennymoor 400kV Substation | Gate not shown to 2; status Awaiting Consents to Consents Approved |
| Spennymoor Greener Grid ParkSpennymoor Grid Solutions Limited | Spennymoor 400kV Substation | Gate not shown to 2; status Scoping to Consents Approved |
| Norwich YareAshgreen Energyfarm Limited | Norwich Main 400kV Substation | moved from Norwich GSP to Norwich Main 400kV Substation; Gate not shown to 2 |
| Achany Extension Wind FarmSse Generation Limited | ACHANY EXTENSION WIND FARM 132/33KV Substation | size 105.0 MW to 81.0 MW; Gate not shown to 1 |
| Sellindge Grid Stability ServicesSellindge Grid Services Limited | Sellindge 400kV Substation | Gate not shown to 2; status Consents Approved to Under Construction/Commissioning |
| Pencloe WindfarmPencloe Wind Energy Limited | Pencloe 132/33kV Substation | size 34.0 MW to 0.0 MW |
| Melksham (Tertiary)Melksham Calne Green Limited | Melksham 400kV Substation | Gate not shown to 2; status Scoping to Under Construction/Commissioning |
| Afan Wind Farm and BESSTrydan Gwyrdd Cymru (Welsh Government) Ltd | SOUTH WALES WEST CONNECTION NODE A 132KV | moved from SOUTH WALES WEST CONNECTION NODE A 132KV SUBSTATION to SOUTH WALES WEST CONNECTION NODE A 132KV |
| Boreland BESSBoreland Energy Ltd | Killin GSP | Gate not shown to 1 |
| Royle Farm BESSAludra Bess Ltd | Drakelow GSP | moved from Drakelow 132kV Substation to Drakelow GSP |
| Witney BESSVoltwise Power Holdings Limited | Chiltern Connection Node C 132kV Substation | moved from Cowley GSP to Chiltern Connection Node C 132kV Substation |
1 joined, 0 left, 1 connection date moved (1 later, 0 earlier), 5 other changes.
| Project | Site | MW | Was | Now | Change |
|---|---|---|---|---|---|
| Creag DhubhMuirden Energy LLP | Clachan 2 132/33kV GSP Substation | 27 | 31 October 2030 | 31 October 2032 | +2.0 yrs |
| Project | Site | Technology | MW | Contracted date | Gate |
|---|---|---|---|---|---|
| Dyce Energy Storage FacilityCbs Energy Storage Assets UK Limited | Dyce 132/33kV Substation | Energy Storage System | 30 | 31 March 2026 | Gate 2 |
None.
| Project | Site | What changed |
|---|---|---|
| Creag Riabhach Wind FarmCreag Riabhach Wind Farm Ltd | Creag Riabhach 132/33kV Substation | Gate 1 to not shown |
| Edinbane WindfarmVattenfall Wind Power Ltd | Edinbane 132/33kV Substation | Gate 1 to not shown |
| PVDP ScarningSolarfour Ltd | North Anglia Connection Node C 400kV Substation | Gate not shown to 1 |
| Cottered - PVDPSolarnine Ltd | West Anglia Connection Node D 400kV Substation | Gate not shown to 1 |
| Creag DhubhMuirden Energy LLP | Clachan 2 132/33kV GSP Substation | size 38.3 MW to 27.0 MW; Gate not shown to 2; status Scoping to Consents Approved |
Want this for your own sites? Queue watch emails you after every new register with what changed at the substations or projects you pick. £99 a month per site, five sites for the price of four.
Start queue watchConfirmed Every row comes from NESO's TEC Register files named above, compared line by line. Transmission connections only. A project can appear as leaving and joining if NESO renumbers it. Dates are the contracted dates in the register, not forecasts.
Contact
Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.
No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.
✓ Received. We will email you within one business day.
Or email info@benzene-group.com