Register changes

What changed in the grid queue

NESO republishes its whole connection register twice a week. We compare each file with the one before and list every project that joined, left, or moved its date. Latest comparison: the register of 23 November 2026 against 19 November 2026.

19 November 2026 to 23 November 2026

2 joined, 2 left, 2 connection dates moved (1 later, 1 earlier), 9 other changes.

Connection dates that moved

ProjectSiteMWWasNowChange
Glen Ullinish Wind FarmGlen Ullinish Wf LimitedGlen Ullinish 132/33kV Substation5016 April 202825 November 2031+3.6 yrs
Lisa's Battery StoragePotencia Energy LimitedMybster 3 132/33kV Substation4731 October 203030 July 2028-2.3 yrs

Joined the queue

ProjectSiteTechnologyMWContracted dateGate
South Humber BankEp UK Power Development Ii LtdSouth Humber Bank 400kV SubstationCCGT (Combined Cycle Gas Turbine)0no dateNo Gate shown
South Humber BankEp UK Power Development Ii LtdSouth Humber Bank 400kV SubstationCCGT (Combined Cycle Gas Turbine)3530 October 2039Gate 1

Left the register

ProjectSiteTechnologyMWWas contracted for
South Humber BankEp UK Power Development Ii LtdSouth Humber Bank 400kV SubstationCCGT (Combined Cycle Gas Turbine)3530 October 2039
Ochill BESSCarlton Power LimitedOchill 132kV SubstationEnergy Storage System5018 August 2028

Gate, size, site and status changes

ProjectSiteWhat changed
Littlebrook BESSEcodev (South) LtdLittlebrook 132kV Substationstatus Scoping to Awaiting Consents
Bilbo FarmLel Bilbo Solar LimitedStrichen 132/33kV GSP Substationstatus Scoping to Consents Approved
Greenburn Mixed TechnologyReg Greenburn LimitedGreenburn Mixed Technology 132kV Substationsize 90.0 MW to 63.0 MW
Glen Ullinish Wind FarmGlen Ullinish Wf LimitedGlen Ullinish 132/33kV SubstationGate not shown to 2
Newarthill Energy ParkDalzell (Newarthill) LtdNewarthill Energy Park 275kV Substationstatus Scoping to Awaiting Consents
Lisa's Battery StoragePotencia Energy LimitedMybster 3 132/33kV SubstationGate not shown to 2; status Awaiting Consents to Consents Approved
Templeton BESSTempleton Battery Storage LimitedLyndhurst GSPstatus Scoping to Consents Approved
Rogerton Cottage BESSDrax Bess Ek LimitedEast Kilbride 275/33kV GSPstatus Scoping to Consents Approved
Welbeck-Newark Solar Farm - PVDPSolarten LtdHigh Marnham 400kV SubstationGate not shown to 1
16 November 2026 to 19 November 2026

1 joined, 3 left, 5 connection dates moved (5 later, 0 earlier), 12 other changes.

Connection dates that moved

ProjectSiteMWWasNowChange
Norwich YareAshgreen Energyfarm LimitedNorwich Main 400kV Substation5018 December 202524 April 2027+1.3 yrs
Sellindge Grid Stability ServicesSellindge Grid Services LimitedSellindge 400kV Substation011 August 202630 October 2027+1.2 yrs
Achany Extension Wind FarmSse Generation LimitedACHANY EXTENSION WIND FARM 132/33KV Substation8130 March 202826 March 2029+1.0 yrs
Spennymoor Greener Grid ParkSpennymoor Grid Solutions LimitedSpennymoor 400kV Substation029 October 20271 October 2028+0.9 yrs
Melksham (Tertiary)Melksham Calne Green LimitedMelksham 400kV Substation5726 June 202631 December 2026+0.5 yrs

Joined the queue

ProjectSiteTechnologyMWContracted dateGate
Templeton BESSTempleton Battery Storage LimitedLyndhurst GSPEnergy Storage System5031 October 2028Gate 2

Left the register

ProjectSiteTechnologyMWWas contracted for
Templeton BESSTempleton Battery Storage LimitedLyndhurst 132/33kVEnergy Storage System3031 October 2027
Templeton BESSTempleton Battery Storage LimitedLyndhurst 132/33kVEnergy Storage System2031 October 2031
Patford Bridge Farm548 UK Investment Holdings LimitedPatford Bridge 400kV SubstationEnergy Storage System;PV Array (Photo Voltaic/solar)20031 October 2033

Gate, size, site and status changes

ProjectSiteWhat changed
Littlebrook BESSEcodev (South) LtdLittlebrook 132kV SubstationGate not shown to 2
Spennymoor Greener Grid ParkSpennymoor Grid Solutions LimitedSpennymoor 400kV SubstationGate not shown to 2; status Awaiting Consents to Consents Approved
Spennymoor Greener Grid ParkSpennymoor Grid Solutions LimitedSpennymoor 400kV SubstationGate not shown to 2; status Scoping to Consents Approved
Norwich YareAshgreen Energyfarm LimitedNorwich Main 400kV Substationmoved from Norwich GSP to Norwich Main 400kV Substation; Gate not shown to 2
Achany Extension Wind FarmSse Generation LimitedACHANY EXTENSION WIND FARM 132/33KV Substationsize 105.0 MW to 81.0 MW; Gate not shown to 1
Sellindge Grid Stability ServicesSellindge Grid Services LimitedSellindge 400kV SubstationGate not shown to 2; status Consents Approved to Under Construction/Commissioning
Pencloe WindfarmPencloe Wind Energy LimitedPencloe 132/33kV Substationsize 34.0 MW to 0.0 MW
Melksham (Tertiary)Melksham Calne Green LimitedMelksham 400kV SubstationGate not shown to 2; status Scoping to Under Construction/Commissioning
Afan Wind Farm and BESSTrydan Gwyrdd Cymru (Welsh Government) LtdSOUTH WALES WEST CONNECTION NODE A 132KVmoved from SOUTH WALES WEST CONNECTION NODE A 132KV SUBSTATION to SOUTH WALES WEST CONNECTION NODE A 132KV
Boreland BESSBoreland Energy LtdKillin GSPGate not shown to 1
Royle Farm BESSAludra Bess LtdDrakelow GSPmoved from Drakelow 132kV Substation to Drakelow GSP
Witney BESSVoltwise Power Holdings LimitedChiltern Connection Node C 132kV Substationmoved from Cowley GSP to Chiltern Connection Node C 132kV Substation
13 November 2026 to 16 November 2026

1 joined, 0 left, 1 connection date moved (1 later, 0 earlier), 5 other changes.

Connection dates that moved

ProjectSiteMWWasNowChange
Creag DhubhMuirden Energy LLPClachan 2 132/33kV GSP Substation2731 October 203031 October 2032+2.0 yrs

Joined the queue

ProjectSiteTechnologyMWContracted dateGate
Dyce Energy Storage FacilityCbs Energy Storage Assets UK LimitedDyce 132/33kV SubstationEnergy Storage System3031 March 2026Gate 2

Left the register

None.

Gate, size, site and status changes

ProjectSiteWhat changed
Creag Riabhach Wind FarmCreag Riabhach Wind Farm LtdCreag Riabhach 132/33kV SubstationGate 1 to not shown
Edinbane WindfarmVattenfall Wind Power LtdEdinbane 132/33kV SubstationGate 1 to not shown
PVDP ScarningSolarfour LtdNorth Anglia Connection Node C 400kV SubstationGate not shown to 1
Cottered - PVDPSolarnine LtdWest Anglia Connection Node D 400kV SubstationGate not shown to 1
Creag DhubhMuirden Energy LLPClachan 2 132/33kV GSP Substationsize 38.3 MW to 27.0 MW; Gate not shown to 2; status Scoping to Consents Approved

Want this for your own sites? Queue watch emails you after every new register with what changed at the substations or projects you pick. £99 a month per site, five sites for the price of four.

Start queue watch

Confirmed Every row comes from NESO's TEC Register files named above, compared line by line. Transmission connections only. A project can appear as leaving and joining if NESO renumbers it. Dates are the contracted dates in the register, not forecasts.

Contact

Name a substation. We will send you its queue, free.

Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.

No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.

✓ Received. We will email you within one business day.

Or email info@benzene-group.com