Sample landowner grid note
A worked example of our £495 landowner grid note, built from real public data. There is no client and no named landowner: the land is a notional field next to Creyke Beck substation, near Cottingham. A real note follows the same six sections and arrives within three working days.
The transmission queue here is long. 7,578 MW is queued at Creyke Beck 400kV across 6 projects, none of it holding Gate 2, with contracted dates running from 2028 to 2039. Confirmed
The local network looks different. Northern Powergrid shows 323 MW of generation headroom at its Creyke Beck grid supply point, rated Green, but rates the nearest 33 kV and most nearby 11 kV substations Red for new generation. Confirmed
A large scheme needing a transmission connection here would join the back of a long queue. A smaller scheme on the local network would be judged mainly on Northern Powergrid's capacity, and the nearest substations are the constrained ones. Only a connection offer settles either. Inferred
| Land | Notional field next to Creyke Beck substation, near Cottingham (sample only) |
|---|---|
| Use being proposed | Solar and battery storage, size not given |
| Proposed buyer or developer | Not shared |
| Register data as of | NESO TEC Register file of 16 November 2026 |
| Local network data as of | Northern Powergrid heat map data, last processed 27 July 2026 |
| Connection site | Distance | MW waiting | Projects | Gate 2 MW | Contracted dates |
|---|---|---|---|---|---|
| Creyke Beck 400kV Substation | At the land | 7,578 | 6 | 0 | 2028 to 2039 |
| Creyke Beck GSP | At the land | 470 | 2 | 0 | 2033 to 2039 |
| Creyke Beck 132kV | At the land | 100 | 1 | 0 | 2034 |
| Birkhill Wood 400kV Substation | About 3 km, position approximate | 4,350 | 3 | 0 | 2030 to 2031 |
| North Humber Connection Nodes6 future nodes | Locations not given in the register | 3,320 | 9 | 0 | 2033 to 2039 |
All rows Confirmed from the NESO TEC Register of 16 November 2026. Distances are straight-line and approximate; cable routes are longer.
| Substation | Type | Distance | Generation headroom MW | Rating | Demand headroom MW | Rating |
|---|---|---|---|---|---|---|
| Creyke Beck | Grid supply point, 132 kV | 0.0 km | 323.3 | Green | 314.8 | Green |
| Beverley 132/33kV | Bulk supply point, 33 kV | 2.2 km | 57.0 | Red | 23.6 | Red |
| Southwood Road | Primary, 11 kV | 2.9 km | 2.2 | Red | 9.5 | Red |
| Endike Lane | Primary, 11 kV | 2.9 km | 23.9 | Red | 11.4 | Red |
| Spark Mill Lane | Primary, 11 kV | 4.0 km | 15.7 | Red | 7.3 | Red |
| County Road North | Primary, 11 kV | 5.1 km | 13.3 | Green | 6.6 | Green |
Confirmed from Northern Powergrid's heat map data, shown as published, with the operator's caveats. Supported by Northern Powergrid Open Data. A substation can show headroom in MW and still be rated Red where a constraint further up the network applies.
What this means. Every project queued at Creyke Beck 400kV is Gate 1 or shows no Gate, so some of it may fall away as NESO applies its readiness tests. We cannot say how much. Inferred
| Project | Site | MW | Technology | Gate | Contracted date | Register status |
|---|---|---|---|---|---|---|
| Creyke Beck Battery 2Cbb Spv Limited | Creyke Beck 400kV | 28 | Battery storage | Not shown | 30 June 2028 | Consents Approved |
| Hornsea Power Station 4Orsted Hornsea Project Four Limited | Creyke Beck 400kV | 2,600 | Offshore wind | Not shown | 30 October 2028: 1,500 MW total 31 October 2029: 2,600 MW total | Scoping |
| CREYKE BECKClean Air Renewables Limited | Creyke Beck 400kV | 500 | Solar + storage | Not shown | 31 May 2033 | Scoping |
| Creyke Beck Solar FarmRWE Renewables UK Solar And Storage Limited | Creyke Beck GSP | 320 | Solar | Not shown | 31 May 2033 | Scoping |
| Hall Ings Farm SubstationO&G Group Limited | Creyke Beck 132kV | 100 | Solar | Not shown | 30 October 2034 | Scoping |
| Creyke Beck PV & BESS SubBeferleah Energy Park Limited | Creyke Beck 400kV | 250 | Solar + storage | Gate 1 | 30 May 2035 | Scoping |
| Bute Hydrogen Project 2Haldane Energy Project 2 Limited | Creyke Beck 400kV | 3,600 | Gas and thermal | Gate 1 | 30 October 2035 | Scoping |
| KENLEY HOUSE SOLAR PARKBoom Developments Ltd | Creyke Beck GSP | 150 | Solar | Not shown | 30 October 2039 | Scoping |
| Flinton RoadFlinton Road Solar Limited | Creyke Beck 400kV | 600 | Solar + storage | Not shown | 31 October 2039 | Scoping |
All rows Confirmed from the NESO TEC Register of 16 November 2026. The developer names are as the register shows them.
Facts first, then our reading. None of this is advice on option terms.
| Source | Used for |
|---|---|
| NESO TEC Register, file of 16 November 2026 | Sections 1 to 3 |
| Northern Powergrid heat map data (Heat Map Data, Table), last processed 27 July 2026 | Section 2, local network |
| NESO, Connections Reform: Supporting your resubmission after initial checks, September 2025 | Section 4, option term |
| NESO, Pro Forma: Option Agreement, Lease Agreement or Existing Land Lease | Section 4, lease term |
Confirmed read on a primary source. Reported taken from a named source we have not checked against the original document. Inferred our reading of confirmed facts. This note uses public data only. Registers change, so findings are correct only as of the dates shown. It does not forecast whether or when a project on this land would connect.
Want one for a real piece of land? A landowner grid note costs £495 for one site and takes three working days. Or start with a free check: tell us the nearest substation and we will send you what is queued there.
Free substation checkContact
Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.
No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.
✓ Received. We will email you within one business day.
Or email info@benzene-group.com