Sample landowner grid note

Land near Creyke Beck, East Riding of Yorkshire

A worked example of our £495 landowner grid note, built from real public data. There is no client and no named landowner: the land is a notional field next to Creyke Beck substation, near Cottingham. A real note follows the same six sections and arrives within three working days.

18 November 2026 · Prepared by Benzene as a sample · A desk review of public registers. Not a valuation, legal advice or an engineering study.

1. The short answer

The transmission queue here is long. 7,578 MW is queued at Creyke Beck 400kV across 6 projects, none of it holding Gate 2, with contracted dates running from 2028 to 2039. Confirmed

The local network looks different. Northern Powergrid shows 323 MW of generation headroom at its Creyke Beck grid supply point, rated Green, but rates the nearest 33 kV and most nearby 11 kV substations Red for new generation. Confirmed

A large scheme needing a transmission connection here would join the back of a long queue. A smaller scheme on the local network would be judged mainly on Northern Powergrid's capacity, and the nearest substations are the constrained ones. Only a connection offer settles either. Inferred

LandNotional field next to Creyke Beck substation, near Cottingham (sample only)
Use being proposedSolar and battery storage, size not given
Proposed buyer or developerNot shared
Register data as ofNESO TEC Register file of 16 November 2026
Local network data as ofNorthern Powergrid heat map data, last processed 27 July 2026

2. The grid near the land

Transmission connection points

Connection siteDistanceMW waitingProjectsGate 2 MWContracted dates
Creyke Beck 400kV SubstationAt the land7,578602028 to 2039
Creyke Beck GSPAt the land470202033 to 2039
Creyke Beck 132kVAt the land100102034
Birkhill Wood 400kV SubstationAbout 3 km, position approximate4,350302030 to 2031
North Humber Connection Nodes6 future nodesLocations not given in the register3,320902033 to 2039

All rows Confirmed from the NESO TEC Register of 16 November 2026. Distances are straight-line and approximate; cable routes are longer.

Local network (Northern Powergrid)

SubstationTypeDistanceGeneration headroom MWRatingDemand headroom MWRating
Creyke BeckGrid supply point, 132 kV0.0 km323.3Green314.8Green
Beverley 132/33kVBulk supply point, 33 kV2.2 km57.0Red23.6Red
Southwood RoadPrimary, 11 kV2.9 km2.2Red9.5Red
Endike LanePrimary, 11 kV2.9 km23.9Red11.4Red
Spark Mill LanePrimary, 11 kV4.0 km15.7Red7.3Red
County Road NorthPrimary, 11 kV5.1 km13.3Green6.6Green

Confirmed from Northern Powergrid's heat map data, shown as published, with the operator's caveats. Supported by Northern Powergrid Open Data. A substation can show headroom in MW and still be rated Red where a constraint further up the network applies.

What this means. Every project queued at Creyke Beck 400kV is Gate 1 or shows no Gate, so some of it may fall away as NESO applies its readiness tests. We cannot say how much. Inferred

3. Who else is queuing here

ProjectSiteMWTechnologyGateContracted dateRegister status
Creyke Beck Battery 2Cbb Spv LimitedCreyke Beck 400kV28Battery storageNot shown30 June 2028Consents Approved
Hornsea Power Station 4Orsted Hornsea Project Four LimitedCreyke Beck 400kV2,600Offshore windNot shown30 October 2028: 1,500 MW total
31 October 2029: 2,600 MW total
Scoping
CREYKE BECKClean Air Renewables LimitedCreyke Beck 400kV500Solar + storageNot shown31 May 2033Scoping
Creyke Beck Solar FarmRWE Renewables UK Solar And Storage LimitedCreyke Beck GSP320SolarNot shown31 May 2033Scoping
Hall Ings Farm SubstationO&G Group LimitedCreyke Beck 132kV100SolarNot shown30 October 2034Scoping
Creyke Beck PV & BESS SubBeferleah Energy Park LimitedCreyke Beck 400kV250Solar + storageGate 130 May 2035Scoping
Bute Hydrogen Project 2Haldane Energy Project 2 LimitedCreyke Beck 400kV3,600Gas and thermalGate 130 October 2035Scoping
KENLEY HOUSE SOLAR PARKBoom Developments LtdCreyke Beck GSP150SolarNot shown30 October 2039Scoping
Flinton RoadFlinton Road Solar LimitedCreyke Beck 400kV600Solar + storageNot shown31 October 2039Scoping

All rows Confirmed from the NESO TEC Register of 16 November 2026. The developer names are as the register shows them.

4. What this means for an option

Facts first, then our reading. None of this is advice on option terms.

  • Gate 2 land test. NESO's guidance says an option agreement used as Gate 2 land evidence needs a minimum term of three years from the date it was signed, unless an exception applies. Confirmed NESO's lease pro forma sets a default lease term of 20 years from the date the option is exercised. Reported
  • Timing. Contracted dates at Creyke Beck run to 2039. If a developer's plan depends on a new transmission connection here, its date could fall after a three to five year option has run. Ask how the two line up. Inferred
  • Local headroom. The grid supply point shows headroom; the nearer 33 kV and 11 kV substations are mostly rated Red. Ask which one the developer would connect to.

5. Questions to put to the developer

  1. Which substation do you plan to connect to, and do you hold a connection offer or have you applied?
  2. If you hold an offer, what is its Gate status and its connection date?
  3. Is the plan a transmission connection at Creyke Beck, or a local connection through Northern Powergrid?
  4. If local, what has Northern Powergrid said about the Red ratings at Beverley and the nearby 11 kV substations?
  5. What happens to the option payments if the connection date moves?

6. Sources and limits

SourceUsed for
NESO TEC Register, file of 16 November 2026Sections 1 to 3
Northern Powergrid heat map data (Heat Map Data, Table), last processed 27 July 2026Section 2, local network
NESO, Connections Reform: Supporting your resubmission after initial checks, September 2025Section 4, option term
NESO, Pro Forma: Option Agreement, Lease Agreement or Existing Land LeaseSection 4, lease term

Confirmed read on a primary source. Reported taken from a named source we have not checked against the original document. Inferred our reading of confirmed facts. This note uses public data only. Registers change, so findings are correct only as of the dates shown. It does not forecast whether or when a project on this land would connect.

Want one for a real piece of land? A landowner grid note costs £495 for one site and takes three working days. Or start with a free check: tell us the nearest substation and we will send you what is queued there.

Free substation check

Contact

Name a substation. We will send you its queue, free.

Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.

No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.

✓ Received. We will email you within one business day.

Or email info@benzene-group.com