So what: Most capacity in the queue is not due until 2031 or later. Before you pay for land, surveys or planning, find the substation nearest your site and check how much is queued there and how long it is waiting. Want it checked for you? Ask for a free substation check.
A reserved seat. Confirmed connection date and point, and a secure place in the reordered queue.
A standby ticket. Indicative date and location only. Can apply for Gate 2 later.
The register's Gate field is blank, so it does not say which.
Confirmed
Which areas are congested, how long the waits are and where they are shorter. Select an area or a site to see it on the map.
Capacity waiting to connect in each area. Bar colour shows the average wait.
Inferred Areas are worked out from each site's map position, which is approximate.
The 10 sites with the most capacity waiting.
Sites with at least 200 MW due on a future date, ranked by the shortest average wait. Projects whose contracted date has already passed are left out.
Inferred A short wait means projects already queued there expect to connect soon. It does not show spare capacity for a new project.
Capacity waiting, by contracted connection year.
How much capacity holds a Gate 2 offer, and what is queued.
Each circle is a connection site. Size shows the capacity waiting to connect there. Colour shows the average wait until the contracted connection date. Select a circle to see who is in the queue.
Tap a circle to see who is queued there. Pinch or use + to zoom in, and drag to move once zoomed. Site names appear as you zoom.
Zoom with the buttons, a double-click, or Ctrl and scroll. Drag to move once zoomed in. Site names appear as you zoom.
Northern Ireland is drawn but not covered. Its grid is run separately by SONI as part of the all-island electricity market, so its connections are not in the NESO register and Gate 1 and Gate 2 do not apply there.
Ranked by capacity waiting to connect, in the view chosen above. Select a row to open the site on the Map tab.
Capacity-weighted years from today to the contracted connection date, by transmission owner area.
These rows place two public registers side by side. They carry no rating and no view on any project. If a match or a figure is wrong, tell us at info@benzene-group.com and we will correct it.
Every figure on this page is computed from the files named below. The only values typed in by hand are the rough map positions that say so.