Free tool · Great Britain transmission queue

See where the grid queue is longest, before you invest

So what: Most capacity in the queue is not due until 2031 or later. Before you pay for land, surveys or planning, find the substation nearest your site and check how much is queued there and how long it is waiting. Want it checked for you? Ask for a free substation check.

What the Gates mean:
Gate 2

A reserved seat. Confirmed connection date and point, and a secure place in the reordered queue.

Gate 1

A standby ticket. Indicative date and location only. Can apply for Gate 2 later.

No Gate shown

The register's Gate field is blank, so it does not say which.

From NESO, connections reform. More on the Gates.

Confirmed

The queue at a glance

Which areas are congested, how long the waits are and where they are shorter. Select an area or a site to see it on the map.

Areas compared

Capacity waiting to connect in each area. Bar colour shows the average wait.

Inferred Areas are worked out from each site's map position, which is approximate.

Most congested sites

The 10 sites with the most capacity waiting.

    Where the wait is shorter

    Sites with at least 200 MW due on a future date, ranked by the shortest average wait. Projects whose contracted date has already passed are left out.

      Inferred A short wait means projects already queued there expect to connect soon. It does not show spare capacity for a new project.

      When the queue is due

      Capacity waiting, by contracted connection year.

      Gate and technology

      How much capacity holds a Gate 2 offer, and what is queued.

      Where the queue is

      Each circle is a connection site. Size shows the capacity waiting to connect there. Colour shows the average wait until the contracted connection date. Select a circle to see who is in the queue.

      Filters and display
      Show
      Colour by
      Contracted to connect by the end of

      Tap a circle to see who is queued there. Pinch or use + to zoom in, and drag to move once zoomed. Site names appear as you zoom.

      Zoom with the buttons, a double-click, or Ctrl and scroll. Drag to move once zoomed in. Site names appear as you zoom.

      Northern Ireland is drawn but not covered. Its grid is run separately by SONI as part of the all-island electricity market, so its connections are not in the NESO register and Gate 1 and Gate 2 do not apply there.