Sample screening report

A 100 MW battery near Case Study Site A

A worked example of our £1,950 screening report, built from real public data. There is no client. The site is an invented 100 MW battery near a 400kV transmission substation in Northern Powergrid's area, which we call Case Study Site A (Site A from here on). Other projects in the queue are Site B, Site C and so on. A real report names the substation and the projects, covers your own site, and arrives within five working days.

21 November 2026 · Prepared by Benzene as a sample · A desk review of public registers and published network data. Not legal advice, an engineering study or a connection offer.

1. Summary

A new 100 MW battery at Site A would join behind 6,555 MW of unbuilt projects at the 400kV substation. None of them holds Gate 2, the earliest contracted date is October 2033, one battery ahead in the queue had its date moved three times in four weeks, and the local network shows no spare capacity at all.

Example site100 MW battery, about 2 km from the Site A 400kV substation (invented for this sample)
ClientNone: sample only
Register data as ofNESO TEC Register file of 16 November 2026
History from26 weekly copies of the register, 19 May to 17 November 2026
Local network data as ofNorthern Powergrid heat map data, last updated 27 July 2026

Four findings that matter most

  1. The queue is long and none of it is Gate 2. Seven unbuilt projects totalling 6,555 MW are contracted to connect directly at the Site A 400kV substation. Three hold Gate 1 (4,400 MW) and four have a blank Gate field (2,155 MW). Their dates run from 30 October 2033 to 30 October 2035. Confirmed
  2. Dates here move, and not always in one direction. A 300 MW battery at the substation (Site B) went from 31 October 2033 to 30 October 2035, then to 31 October 2031, then back to 30 October 2035, across four weekly copies in October and November 2026. Reported
  3. The local network is full too. Northern Powergrid shows 0 MW of generation headroom and 0 of demand headroom at the Site A grid supply point and at all 19 substations below it, and rates the transmission side red for known National Grid constraints. Confirmed
  4. Staying in the queue may soon cost money. Ofgem has proposed a battery commitment fee from £3,000 per MW, rising to a maximum of £25,000 per MW. On 100 MW that is £300,000 at the start and up to £2.5m at the cap. It is a proposal, not a decision. Confirmed fee, Inferred arithmetic.

Three things to check before relying on a date here

  1. Ask National Grid Electricity Transmission and NESO what reinforcement works the Site A dates depend on, and whether a new Gate 2 application would be assessed before or after the existing Gate 1 entries.
  2. Ask Northern Powergrid when the transmission constraint at the grid supply point is expected to lift, and whether a flexible or non-firm distribution connection is on offer in the meantime.
  3. Ask the landowner and your lawyer whether the option long-stop date allows for a connection date in the mid-2030s.

2. Issue summary

AreaFlagStatusHeadline
Queue lengthOpen issueConfirmed6,555 MW unbuilt at 400kV, none Gate 2
Date stabilityOpen issueReportedOne battery's date moved three times in four weeks; net 24 months later over six months
Local headroomOpen issueConfirmed0 MW generation and 0 demand headroom at the grid supply point and all 19 substations below; transmission constraint rated red
Fee exposureOpen issueInferred£300,000 to £2.5m on 100 MW under Ofgem's proposal
Gate 2 readinessNot assessedNeeds the client's land documents
Distribution offer batchesClearInferredSite A is outside the area covered by National Grid's distribution offer schedule
Constraints and chargesNot assessedCovered in a client report

Clear: nothing in public sources conflicts with the plan. Open issue: public sources point to a risk. Not assessed: we have not read a primary source for it in this sample.

3. The example site

TechnologyBattery storage, 100 MW
LocationInvented. Land near the Site A 400kV substation
Connection routesDirect to the 400kV substation (transmission), or through Northern Powergrid's network at the Site A grid supply point (distribution)
Network operatorsTransmission: National Grid Electricity Transmission. Distribution: Northern Powergrid. Confirmed

4. Queue at the connection point

Site A appears in the register under four site names: the 400kV substation, a 132kV substation and two grid supply point entries. Most of the queue is at the 400kV substation.

SiteTechnologyMWGateContracted dateRegister status
Site DBattery and solar249Not shown30 Oct 2033Scoping
Site EBattery and solar500Not shown30 Jun 2034Scoping
Site FBattery and solar500Not shown30 Oct 2034Scoping
Site CBattery500Gate 130 Apr 2035Scoping
Site GGas (CCGT) with demand906Not shown30 May 2035Scoping
Site HGas (CCGT)3,600Gate 130 Oct 2035Scoping
Site BBattery300Gate 130 Oct 2035Scoping
Total6,555

Unbuilt projects connecting directly at the Site A 400kV substation. NESO TEC Register, 16 November 2026. Confirmed

SiteEntryTechnologyMWGateContracted dateStatus
Site I132kV substationSolar150Gate 131 Oct 2035Awaiting Consents
Site JGrid supply pointSolar180Gate 130 Oct 2035Scoping
Site K132kV substationGas (CCGT)40 connectedBuilt
Site L400/132kV grid supply pointBattery80 connectedBuilt

Other Site A entries, connecting through the distribution network. NESO TEC Register, 16 November 2026. Confirmed

Gate mix at 400kV. Gate 1: 4,400 MW in three projects. No Gate shown: 2,155 MW in four. Gate 2: none. Batteries, alone or with solar, make up 2,049 MW of the 6,555 MW. Confirmed

What this means. A blank Gate field means the register shows no Gate result for that project; on its own it does not mean the project has left the process. Every project ahead is at Scoping, and public sources do not say which will receive a Gate 2 offer, so the queue a new applicant would sit behind could be much shorter or the same length. We make no forecast in this sample. Inferred

5. Six months of history

NESO publishes only the current register. We keep weekly copies, so we can see how dates have moved. The six months to 17 November 2026 at Site A:

Week of copySiteTechnology, MWChange
9 Jun 2026Site ISolar, 150Entry moved from the grid supply point to the 132kV substation
9 Jun 2026Site MBattery, 240Moved away from Site A to a different connection point
16 Jun 2026Sites I and JSolar, 150 and 180Gate field filled as Gate 1
13 Oct 2026Site BBattery, 30031 Oct 2033 to 30 Oct 2035 (24 months later)
13 Oct 2026Site CBattery, 50030 Apr 2035 to 30 Oct 2035 (6 months later); Gate field filled as Gate 1
13 Oct 2026Site HGas, 3,60031 Oct 2035 to 30 Oct 2035 (one day earlier)
20 Oct 2026Site BBattery, 30030 Oct 2035 to 31 Oct 2031 (48 months earlier)
20 Oct 2026Site CBattery, 50030 Oct 2035 back to 30 Apr 2035
3 Nov 2026Site BBattery, 30031 Oct 2031 to 30 Oct 2035 (48 months later)

Weekly copies of the NESO register from a public archive; the 17 November copy matched our own NESO download row for row. Earlier copies not yet checked against NESO. Reported

Across the substation's three projects with date moves, the register recorded six moves (three later, three earlier), a net change of about 24 months later. Site A had the second highest number of date moves of any connection site in the register over those six months. Reported

What this means. The October moves came while Gate 2 offers were being issued. Public sources do not say whether Site B's 20 October date was an offer, a correction or a data error. One register file is a snapshot: check a date against more than one file before relying on it. Inferred

6. The local network

Northern Powergrid publishes the data behind its network availability heat maps. We read every entry under the Site A grid supply point.

Firm capacity at the grid supply point260 MVA
Maximum net demand seen181
Generation connected or accepted downstream607.9 MW
Demand connected or accepted downstream115.5 MVA
Generation headroom0 None
Demand headroom0 None
National Grid constraint ratingRed known transmission constraints
The 19 substations below it0 generation and 0 demand headroom at every one; each limited by the grid supply point or the site above it. Local fault level: 16 green, 1 amber, 2 red

Northern Powergrid, Heat Map Data: Table, last updated 27 July 2026, read 21 November 2026, shown as published. Confirmed

What this means. A distribution connection is no shortcut here. The operator shows no thermal headroom at the grid supply point or anywhere below it and names the transmission network as the limit. Generation already connected or accepted below the grid supply point is more than twice its firm capacity. A 100 MW battery is likely to wait on transmission reinforcement whichever route it takes, unless a flexible or non-firm offer is available. Inferred

7. Fee exposure

ItemFinding
Starting fee£3,000 per MW Confirmed
Steps£5,000 per MW after six months if not deactivated, then up by £5,000 per MW every six months Confirmed
Cap£25,000 per MW, if oversubscription persists Confirmed
When it appliesWhere a technology exceeds its target requirement by more than 50%; it stops once oversubscription falls below 25% Confirmed
On energisationReturned to the project Confirmed
StatusA minded-to proposal; decision expected later in 2026. No final decision found by 21 November 2026 Confirmed
Distribution-connected batteriesNot established from the parts of the consultation we read

For 100 MW: £300,000 at the start (100 × £3,000), £500,000 after six months (100 × £5,000), £2.5m at the cap (100 × £25,000). Inferred Every date in the Site A 400kV queue is in or after October 2033, so a developer will want to know how long that money could be held.

8. Gate 2 readiness

Empty in a public sample: there are no land documents. In a client report we check your option or lease line by line against NESO's Gate 2 criteria (land rights, red line boundary, minimum acreage for the technology and MW) and list every gap.

9. Constraints and charges

Not assessed in this sample. A client report adds the charging zone and tariff outlook, the constraint record on nearby boundaries and the reinforcements planned, with an engineer's view of the likely effect on revenue.

10. What we could not establish

QuestionWho can answer it
Which reinforcement works do the Site A dates depend on, and when will the transmission constraint lift?National Grid Electricity Transmission, NESO, Northern Powergrid
Why did Site B's date move to 2031 for two weeks in October, then back?NESO, the developer
What do the four blank Gate fields mean for those projects' place in the queue?NESO
Has local headroom changed since the operator's July 2026 update?Northern Powergrid
Would Ofgem's battery fee apply to a battery connecting through the distribution network?Ofgem's final decision; your lawyer
How much output would a battery here lose to constraints?A chartered power engineer, from a network study

11. Sources and limits

SourceUsed for
NESO TEC Register, file of 16 November 2026 (our own download)Sections 1, 2 and 4
Weekly copies of the TEC Register, 19 May to 17 November 2026Section 5
Northern Powergrid, Heat Map Data: Table, last updated 27 July 2026 (Northern Powergrid Open Data Licence)Section 6
Ofgem press release, 17 September 2026Section 7
Ofgem, CMP470 minded-to consultation, 17 September 2026Section 7

Confirmed read on a primary source. Reported from a named source or register copies not yet checked against NESO. Inferred our reading of confirmed facts. We do not forecast connection dates. Registers change, so findings are correct only as of the dates shown. Not legal advice, an engineering study or investment advice. Not yet reviewed by a chartered engineer.

Weighing a real site? A screening report costs £1,950 and takes five working days, for your site and your substation. Or start with a free check: tell us the nearest substation and we will send you what is queued there.

Free substation check

Contact

Name a substation. We will send you its queue, free.

Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.

No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.

✓ Received. We will email you within one business day.

Or email info@benzene-group.com