Sample screening report
A worked example of our £1,950 screening report, built from real public data. There is no client. The site is an invented 100 MW battery near a 400kV transmission substation in Northern Powergrid's area, which we call Case Study Site A (Site A from here on). Other projects in the queue are Site B, Site C and so on. A real report names the substation and the projects, covers your own site, and arrives within five working days.
A new 100 MW battery at Site A would join behind 6,555 MW of unbuilt projects at the 400kV substation. None of them holds Gate 2, the earliest contracted date is October 2033, one battery ahead in the queue had its date moved three times in four weeks, and the local network shows no spare capacity at all.
| Example site | 100 MW battery, about 2 km from the Site A 400kV substation (invented for this sample) |
|---|---|
| Client | None: sample only |
| Register data as of | NESO TEC Register file of 16 November 2026 |
| History from | 26 weekly copies of the register, 19 May to 17 November 2026 |
| Local network data as of | Northern Powergrid heat map data, last updated 27 July 2026 |
| Area | Flag | Status | Headline |
|---|---|---|---|
| Queue length | Open issue | Confirmed | 6,555 MW unbuilt at 400kV, none Gate 2 |
| Date stability | Open issue | Reported | One battery's date moved three times in four weeks; net 24 months later over six months |
| Local headroom | Open issue | Confirmed | 0 MW generation and 0 demand headroom at the grid supply point and all 19 substations below; transmission constraint rated red |
| Fee exposure | Open issue | Inferred | £300,000 to £2.5m on 100 MW under Ofgem's proposal |
| Gate 2 readiness | Not assessed | Needs the client's land documents | |
| Distribution offer batches | Clear | Inferred | Site A is outside the area covered by National Grid's distribution offer schedule |
| Constraints and charges | Not assessed | Covered in a client report |
Clear: nothing in public sources conflicts with the plan. Open issue: public sources point to a risk. Not assessed: we have not read a primary source for it in this sample.
| Technology | Battery storage, 100 MW |
|---|---|
| Location | Invented. Land near the Site A 400kV substation |
| Connection routes | Direct to the 400kV substation (transmission), or through Northern Powergrid's network at the Site A grid supply point (distribution) |
| Network operators | Transmission: National Grid Electricity Transmission. Distribution: Northern Powergrid. Confirmed |
Site A appears in the register under four site names: the 400kV substation, a 132kV substation and two grid supply point entries. Most of the queue is at the 400kV substation.
| Site | Technology | MW | Gate | Contracted date | Register status |
|---|---|---|---|---|---|
| Site D | Battery and solar | 249 | Not shown | 30 Oct 2033 | Scoping |
| Site E | Battery and solar | 500 | Not shown | 30 Jun 2034 | Scoping |
| Site F | Battery and solar | 500 | Not shown | 30 Oct 2034 | Scoping |
| Site C | Battery | 500 | Gate 1 | 30 Apr 2035 | Scoping |
| Site G | Gas (CCGT) with demand | 906 | Not shown | 30 May 2035 | Scoping |
| Site H | Gas (CCGT) | 3,600 | Gate 1 | 30 Oct 2035 | Scoping |
| Site B | Battery | 300 | Gate 1 | 30 Oct 2035 | Scoping |
| Total | 6,555 |
Unbuilt projects connecting directly at the Site A 400kV substation. NESO TEC Register, 16 November 2026. Confirmed
| Site | Entry | Technology | MW | Gate | Contracted date | Status |
|---|---|---|---|---|---|---|
| Site I | 132kV substation | Solar | 150 | Gate 1 | 31 Oct 2035 | Awaiting Consents |
| Site J | Grid supply point | Solar | 180 | Gate 1 | 30 Oct 2035 | Scoping |
| Site K | 132kV substation | Gas (CCGT) | 40 connected | Built | ||
| Site L | 400/132kV grid supply point | Battery | 80 connected | Built |
Other Site A entries, connecting through the distribution network. NESO TEC Register, 16 November 2026. Confirmed
Gate mix at 400kV. Gate 1: 4,400 MW in three projects. No Gate shown: 2,155 MW in four. Gate 2: none. Batteries, alone or with solar, make up 2,049 MW of the 6,555 MW. Confirmed
What this means. A blank Gate field means the register shows no Gate result for that project; on its own it does not mean the project has left the process. Every project ahead is at Scoping, and public sources do not say which will receive a Gate 2 offer, so the queue a new applicant would sit behind could be much shorter or the same length. We make no forecast in this sample. Inferred
NESO publishes only the current register. We keep weekly copies, so we can see how dates have moved. The six months to 17 November 2026 at Site A:
| Week of copy | Site | Technology, MW | Change |
|---|---|---|---|
| 9 Jun 2026 | Site I | Solar, 150 | Entry moved from the grid supply point to the 132kV substation |
| 9 Jun 2026 | Site M | Battery, 240 | Moved away from Site A to a different connection point |
| 16 Jun 2026 | Sites I and J | Solar, 150 and 180 | Gate field filled as Gate 1 |
| 13 Oct 2026 | Site B | Battery, 300 | 31 Oct 2033 to 30 Oct 2035 (24 months later) |
| 13 Oct 2026 | Site C | Battery, 500 | 30 Apr 2035 to 30 Oct 2035 (6 months later); Gate field filled as Gate 1 |
| 13 Oct 2026 | Site H | Gas, 3,600 | 31 Oct 2035 to 30 Oct 2035 (one day earlier) |
| 20 Oct 2026 | Site B | Battery, 300 | 30 Oct 2035 to 31 Oct 2031 (48 months earlier) |
| 20 Oct 2026 | Site C | Battery, 500 | 30 Oct 2035 back to 30 Apr 2035 |
| 3 Nov 2026 | Site B | Battery, 300 | 31 Oct 2031 to 30 Oct 2035 (48 months later) |
Weekly copies of the NESO register from a public archive; the 17 November copy matched our own NESO download row for row. Earlier copies not yet checked against NESO. Reported
Across the substation's three projects with date moves, the register recorded six moves (three later, three earlier), a net change of about 24 months later. Site A had the second highest number of date moves of any connection site in the register over those six months. Reported
What this means. The October moves came while Gate 2 offers were being issued. Public sources do not say whether Site B's 20 October date was an offer, a correction or a data error. One register file is a snapshot: check a date against more than one file before relying on it. Inferred
Northern Powergrid publishes the data behind its network availability heat maps. We read every entry under the Site A grid supply point.
| Firm capacity at the grid supply point | 260 MVA |
|---|---|
| Maximum net demand seen | 181 |
| Generation connected or accepted downstream | 607.9 MW |
| Demand connected or accepted downstream | 115.5 MVA |
| Generation headroom | 0 None |
| Demand headroom | 0 None |
| National Grid constraint rating | Red known transmission constraints |
| The 19 substations below it | 0 generation and 0 demand headroom at every one; each limited by the grid supply point or the site above it. Local fault level: 16 green, 1 amber, 2 red |
Northern Powergrid, Heat Map Data: Table, last updated 27 July 2026, read 21 November 2026, shown as published. Confirmed
What this means. A distribution connection is no shortcut here. The operator shows no thermal headroom at the grid supply point or anywhere below it and names the transmission network as the limit. Generation already connected or accepted below the grid supply point is more than twice its firm capacity. A 100 MW battery is likely to wait on transmission reinforcement whichever route it takes, unless a flexible or non-firm offer is available. Inferred
| Item | Finding |
|---|---|
| Starting fee | £3,000 per MW Confirmed |
| Steps | £5,000 per MW after six months if not deactivated, then up by £5,000 per MW every six months Confirmed |
| Cap | £25,000 per MW, if oversubscription persists Confirmed |
| When it applies | Where a technology exceeds its target requirement by more than 50%; it stops once oversubscription falls below 25% Confirmed |
| On energisation | Returned to the project Confirmed |
| Status | A minded-to proposal; decision expected later in 2026. No final decision found by 21 November 2026 Confirmed |
| Distribution-connected batteries | Not established from the parts of the consultation we read |
For 100 MW: £300,000 at the start (100 × £3,000), £500,000 after six months (100 × £5,000), £2.5m at the cap (100 × £25,000). Inferred Every date in the Site A 400kV queue is in or after October 2033, so a developer will want to know how long that money could be held.
Empty in a public sample: there are no land documents. In a client report we check your option or lease line by line against NESO's Gate 2 criteria (land rights, red line boundary, minimum acreage for the technology and MW) and list every gap.
Not assessed in this sample. A client report adds the charging zone and tariff outlook, the constraint record on nearby boundaries and the reinforcements planned, with an engineer's view of the likely effect on revenue.
| Question | Who can answer it |
|---|---|
| Which reinforcement works do the Site A dates depend on, and when will the transmission constraint lift? | National Grid Electricity Transmission, NESO, Northern Powergrid |
| Why did Site B's date move to 2031 for two weeks in October, then back? | NESO, the developer |
| What do the four blank Gate fields mean for those projects' place in the queue? | NESO |
| Has local headroom changed since the operator's July 2026 update? | Northern Powergrid |
| Would Ofgem's battery fee apply to a battery connecting through the distribution network? | Ofgem's final decision; your lawyer |
| How much output would a battery here lose to constraints? | A chartered power engineer, from a network study |
| Source | Used for |
|---|---|
| NESO TEC Register, file of 16 November 2026 (our own download) | Sections 1, 2 and 4 |
| Weekly copies of the TEC Register, 19 May to 17 November 2026 | Section 5 |
| Northern Powergrid, Heat Map Data: Table, last updated 27 July 2026 (Northern Powergrid Open Data Licence) | Section 6 |
| Ofgem press release, 17 September 2026 | Section 7 |
| Ofgem, CMP470 minded-to consultation, 17 September 2026 | Section 7 |
Confirmed read on a primary source. Reported from a named source or register copies not yet checked against NESO. Inferred our reading of confirmed facts. We do not forecast connection dates. Registers change, so findings are correct only as of the dates shown. Not legal advice, an engineering study or investment advice. Not yet reviewed by a chartered engineer.
Weighing a real site? A screening report costs £1,950 and takes five working days, for your site and your substation. Or start with a free check: tell us the nearest substation and we will send you what is queued there.
Free substation checkContact
Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.
No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.
✓ Received. We will email you within one business day.
Or email info@benzene-group.com