How it works

Why grid dates matter, and how we check them

What a late connection costs, what the labels in the national register really mean, and where every figure we publish comes from.

Why it matters

A bad grid date costs money long before anyone notices

Land options, surveys and planning applications are paid for up front. If the site cannot connect for ten years, that money is tied up or lost, and someone signed off on it. The answer is in public records, but it is spread across registers that few people have time to read. A short, sourced report means the decision rests on evidence, not on a guess.

1

Drop weak sites early

TodayDownload a 2,000-row spreadsheet and filter it by hand, or apply and wait months for an offer.
With BenzeneThe queue, the wait and the competition at the substations near your site, in one report.

So what: you stop paying for sites that cannot connect in time.

2

See who is ahead of you

TodayCompeting projects are buried in the register, under company names that change.
With BenzeneEvery project at the substation, its size, its Gate, its date and who holds it.

So what: you know your real place in the line before you negotiate land or finance.

3

Check the dates you rely on

TodayA developer's stated date, a news story, or nothing at all.
With BenzeneThe register date set against the planning record, the revenue contract and the grid works it depends on.

So what: you catch a date that has drifted before it costs you. In one project we checked, three public sources gave dates more than three years apart.

A screening report costs £1,950, fixed. Set that against months of option payments, surveys and a planning application on a site that cannot connect. If the report does not answer the brief, you do not pay.

Ask about a site

What would a late grid date cost you?

Put in your own figures. Nothing is sent anywhere; the sum runs in your browser.

Enter both figures to see the total.

Gates explained

Gate 1, Gate 2 and blank: what the labels in the register mean

Since connections reform, NESO sorts the queue by whether a project is ready and needed. The label tells you how firm a project's date and place in the queue are. Think of it as the difference between a reserved seat and a standby ticket.

Gate 2

firm

A firm offer, for projects that showed NESO they are ready (for example, land secured) and needed for the 2030 clean power plan.

  • Confirmed connection date
  • Confirmed connection point
  • Secure place in the reordered queue

143 unbuilt projects, 26.5 GW. Average wait 1.5 years.

Gate 1

indicative

A holding position for projects not yet ready or needed. They can apply for Gate 2 later.

  • Indicative date only, which can move
  • Indicative location only
  • No firm place in the queue

928 unbuilt projects, 333.7 GW. Average wait 8.1 years.

Blank

not stated

The register's Gate field is empty. The register does not say why, so we do not treat these as either gate.

  • Status not stated in the register
  • Ask the project or NESO before relying on it

604 unbuilt projects, 231.7 GW.

ConfirmedDefinitions: NESO, connections reform. Figures: our analysis of the NESO TEC Register, 23 November 2026.

When the queue is due to connect

Capacity by contracted connection year. Gate 2 projects are mostly due by 2029 (86% of Gate 2 capacity). Most of the rest is dated 2031 or later.

Gate 2Gate 1Blank

How we work

Primary sources, tagged and checked before release

We read the registers themselves, not the press. Our research is produced with AI systems that read and cross-reference the source files, and every report is reviewed before it is sent.

Confirmed read directly from a primary source, such as a register or a regulator's letter
Reported from a named secondary source, not yet confirmed at source
Inferred our own deduction from confirmed facts, with the reasoning shown

We report what public records say. We do not give engineering, legal or investment advice.

Sources we read

NESO TEC RegisterNESO connections reformNESO balancing costsOfgem decisionsRenewable Energy Planning DatabaseCfD register (LCCC)Council and Scottish Government planning recordsCompanies House

In plain English

New wind farms, solar parks and batteries cannot plug into the grid whenever they like. They join a queue, and right now about 592 GW of projects are in it.

The queue is public, but it lives in large spreadsheets and documents that change every week. We read them, work out what changed, and tell you what it means for the site you care about, with the sources attached so you can check.

And yes, we named a grid company after a molecule.

Contact

Name a substation. We will send you its queue, free.

Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.

No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.

✓ Received. We will email you within one business day.

Or email info@benzene-group.com