How it works
What a late connection costs, what the labels in the national register really mean, and where every figure we publish comes from.
Why it matters
Land options, surveys and planning applications are paid for up front. If the site cannot connect for ten years, that money is tied up or lost, and someone signed off on it. The answer is in public records, but it is spread across registers that few people have time to read. A short, sourced report means the decision rests on evidence, not on a guess.
So what: you stop paying for sites that cannot connect in time.
So what: you know your real place in the line before you negotiate land or finance.
So what: you catch a date that has drifted before it costs you. In one project we checked, three public sources gave dates more than three years apart.
A screening report costs £1,950, fixed. Set that against months of option payments, surveys and a planning application on a site that cannot connect. If the report does not answer the brief, you do not pay.
Ask about a sitePut in your own figures. Nothing is sent anywhere; the sum runs in your browser.
Enter both figures to see the total.
Gates explained
Since connections reform, NESO sorts the queue by whether a project is ready and needed. The label tells you how firm a project's date and place in the queue are. Think of it as the difference between a reserved seat and a standby ticket.
A firm offer, for projects that showed NESO they are ready (for example, land secured) and needed for the 2030 clean power plan.
Like a reserved seat. You know where you sit and when the show starts.
143 unbuilt projects, 26.5 GW. Average wait 1.5 years.
A holding position for projects not yet ready or needed. They can apply for Gate 2 later.
Like a standby ticket. You are in the building, but your seat and time can change.
928 unbuilt projects, 333.7 GW. Average wait 8.1 years.
The register's Gate field is empty. The register does not say why, so we do not treat these as either gate.
No ticket shown. The register does not say which kind it holds.
604 unbuilt projects, 231.7 GW.
ConfirmedDefinitions: NESO, connections reform. Figures: our analysis of the NESO TEC Register, 23 November 2026.
Capacity by contracted connection year. Gate 2 projects are mostly due by 2029 (86% of Gate 2 capacity). Most of the rest is dated 2031 or later.
How we work
We read the registers themselves, not the press. Our research is produced with AI systems that read and cross-reference the source files, and every report is reviewed before it is sent.
We report what public records say. We do not give engineering, legal or investment advice.
New wind farms, solar parks and batteries cannot plug into the grid whenever they like. They join a queue, and right now about 592 GW of projects are in it.
The queue is public, but it lives in large spreadsheets and documents that change every week. We read them, work out what changed, and tell you what it means for the site you care about, with the sources attached so you can check.
And yes, we named a grid company after a molecule.
Contact
Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.
No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.
✓ Received. We will email you within one business day.
Or email info@benzene-group.com