Sample data centre power brief
A worked example of our data centre power brief, built from real public data. There is no client. We picked three areas near transmission substations as examples of different kinds of location; nothing here says a data centre is planned at any of them. A real brief compares up to three sites of your choosing and arrives within seven working days.
None of this says whether 100 MW of demand can connect at any of them. NESO's register lists generation and storage, not demand applications. That is a question for NESO and the network operator, and section 6 lists what to ask. Inferred
| Request modelled | A 100 MW data centre, comparing three candidate areas |
|---|---|
| Client | None: sample only |
| Register data as of | NESO TEC Register file of 16 November 2026 |
| Local network data as of | Northern Powergrid, last processed 27 July 2026; SSEN Distribution, March 2026. National Grid Electricity Distribution not yet covered. |
| Area | Register rows | Connected MW | Queued MW | Queued MW by Gate | Contracted dates (queued) |
|---|---|---|---|---|---|
| Blyth, Northumberland | 5 | 396 | 3,650 | Gate 1: 1,850 No Gate shown: 1,800 | Nov 2029 to Oct 2036 |
| Ratcliffe-on-Soar, Nottinghamshire | 7 | 266.76 | 909.9 | Gate 1: 639.9 No Gate shown: 270 | Oct 2028 to Oct 2033 |
| Didcot, Oxfordshire | 8 | 1,579 | 1,179.9 | Gate 2: 300 Gate 1: 429.9 No Gate shown: 450 | Mar 2027 to Oct 2037 |
Confirmed from the NESO TEC Register of 16 November 2026. The counts and sums are ours, over every row whose connection site name contains the area name. "Queued" is the MW increase not yet connected.
| Project | MW | Technology | Gate | Contracted date | Register status |
|---|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm CBlyth 400kV Substation | 1,800 queued | Offshore wind | Not shown | 30 November 2029 | Scoping |
| Icewind BlythBlyth 400kV Substation | 1,000 queued | Offshore wind | Gate 1 | 31 October 2031 | Scoping |
| Blyth BESSBlyth 275kV Substation | 450 queued | Storage | Gate 1 | 31 October 2036 | Scoping |
| Hope Battery StorageBlyth 400kV Substation | 400 queued | Storage | Gate 1 | 31 October 2036 | Scoping |
| Lynemouth Power StationBlyth GSP | 396 connected | Biomass | Built |
| Project | MW | Technology | Gate | Contracted date | Register status |
|---|---|---|---|---|---|
| Whatton EstateRatcliffe GSP | 130 queued | Storage, Solar | Not shown | 30 October 2028 | Scoping |
| EMERGE CentreRatcliffe-on-Soar 132kV Substation | 49.9 queued | Waste | Gate 1 | 29 June 2029 | Scoping |
| Ratcliffe Kegworth Road BEGARatcliffe-on-Soar 132kV Substation | 140 queued | Storage, Solar | Not shown | 30 October 2033 | Scoping |
| Ratcliffe-on-Soar IIRatcliffe-on-Soar 400kV Substation | 590 queued | Storage, Solar | Gate 1 | 30 October 2033 | Scoping |
| Ratcliffe on SoarRatcliffe-on-Soar 400kV Substation | 225 connected | Storage, Gas turbine (OCGT) | Built | ||
| Redfield Road ARatcliffe GSP | 20.88 connected | CHP | Built | ||
| Redfield Road BRatcliffe GSP | 20.88 connected | Thermal | Built |
| Project | MW | Technology | Gate | Contracted date | Register status |
|---|---|---|---|---|---|
| Didcot BatteryDidcot 400/132kV Substation | 100 queued | Demand, Storage | Gate 1 | 31 March 2027 | Scoping |
| Didcot Energy ParkDidcot 400kV Substation | 300 queued | Storage | Not shown | 31 October 2027 | Awaiting Consents |
| Didcot RoadDidcot 400kV Substation | 300 queued | Storage | Gate 2 | 31 October 2028 | Consents Approved |
| Didcot BDidcot 400kV Substation | 230 queued (plus 1,475 connected) | Gas (CCGT), Storage | Gate 1 | 31 October 2037 | Built |
| Didcot BESS 2Didcot 132kV GIS Substation | 99.9 queued | Storage | Gate 1 | 31 October 2037 | Scoping |
| Sutton CourtenayDidcot 132kV Substation | 150 queued | Demand, Storage | Not shown | 31 October 2037 | Scoping |
| Didcot A GTsDidcot 400kV Substation | 100 connected | Gas turbine (OCGT) | Built | ||
| PeakGen BEGA - DidcotDidcot GSP | 4 connected | Oil and gas turbine | Built |
All rows Confirmed from the NESO TEC Register of 16 November 2026, names as the register shows them. Two Didcot storage rows list "Demand" in their plant type; that is battery import, not a data centre. No changes at any of the three areas between the registers of 13 and 16 November.
| Substation | Type | Distance | Generation headroom MW | Rating | Demand headroom MW | Rating |
|---|---|---|---|---|---|---|
| Blyth | Grid supply point, 132 kV | At the GSP | 0.0 | Amber | 45.8 | Amber |
| Blyth | Grid supply point, 66 kV | At the GSP | 0.0 | Green | 0.0 | Green |
| Maddison Street | Primary, 11 kV | 1.7 km | 0.0 | Green | 0.0 | Green |
| Wansbeck | Primary, 11 kV | 2.1 km | 0.0 | Amber | 0.0 | Amber |
| Reservoir | Primary, 20 kV | 4.2 km | 0.0 | Amber | 0.0 | Green |
| Ashington | Primary, 11 kV | 4.3 km | 0.0 | Red | 0.0 | Amber |
Northern Powergrid, Heat map data, last processed 27 July 2026, read 19 November 2026, shown as published. Distances are straight-line and approximate.
| Substation | Type | Distance | Generation headroom MW | Rating | Demand headroom MVA | Rating |
|---|---|---|---|---|---|---|
| Milton | Primary, 33 kV | 0.9 km | 0.0 | Red | 0.0 | Red |
| Drayton | Bulk supply point, 132 kV | 4.3 km | 0.0 | Red | 0.0 | Red |
| Fulscot | Primary, 33 kV | 4.3 km | 0.0 | Red | 0.0 | Red |
| Culham | Primary, 132 kV | 4.8 km | 0.0 | Red | 15.5 | Green |
| Winsmore Lane | Primary, 33 kV | 5.3 km | 0.0 | Red | 0.0 | Red |
| Harwell | Primary, 132 kV | 6.0 km | 0.0 | Red | 39.1 | Green |
SSEN Distribution, Headroom Dashboard Data, March 2026, read 19 November 2026, shown as published. Distances are straight-line and approximate.
Not yet covered. We have asked National Grid Electricity Distribution to confirm the licence terms for its headroom data before we show it. A real brief would say the same, or quote the operator's own map with its date.
What this means. Local substations near Blyth and Didcot show tens of MW of demand headroom at most, and often none. 100 MW is a transmission-scale request: the local network is a guide to how tight the area is, not a route to connection. Inferred
Confirmed from each operator's published data, shown as published, with the operator's caveats. Northern Powergrid: Supported by Northern Powergrid Open Data. SSEN: Contains SSEN Distribution data, CC BY 4.0; SSEN gives demand headroom in MVA. Operators work out headroom their own way, so compare within an area rather than across them.
This sample lists only projects on the same substations and grid supply points (section 2). A real brief adds register projects within about 10 km, for co-location or private wire conversations.
| Blyth | Ratcliffe-on-Soar | Didcot | |
|---|---|---|---|
| Queued MW at node Confirmed | 3,650 | 909.9 | 1,179.9 |
| Gate 2 MW queued Confirmed | 0 | 0 | 300 |
| Latest queued date Confirmed | Oct 2036 | Oct 2033 | Oct 2037 |
| Connected at node Confirmed | 396 MW | 266.76 MW | 1,579 MW |
| Best local demand headroom nearby Confirmed | 45.8 MW (Blyth 132 kV GSP, Amber) | Not yet covered | 39.1 MVA (Harwell, Green) |
| Fee at 100 MW, if adopted Inferred | £23.75m to £71.25m | Same | Same |
| Source | Used for |
|---|---|
| NESO TEC Register, file of 16 November 2026 | Sections 1, 2 and 7 |
| Northern Powergrid heat map data, last processed 27 July 2026 | Section 3, Blyth |
| SSEN Distribution, Headroom Dashboard Data, March 2026 | Section 3, Didcot |
| Ofgem, Curate: Demand Connections Reform consultation, 29 July 2026 | Section 5, fee |
| HM Treasury, The Data Centre Covenant, 28 October 2026 | Section 5, Covenant |
Confirmed read on a primary source. Reported taken from a named source we have not checked against the original. Inferred our reading of confirmed facts. The register lists generation and storage, not demand, and we have seen no demand offer at these sites. We do not forecast connection dates. Registers change, so findings are correct only as of the dates shown. Not legal advice or an engineering study.
Weighing real sites? A data centre power brief costs £2,950 for up to three sites, or £1,950 for one, and takes seven working days. Or start with a free check: tell us the nearest substation and we will send you what is queued there.
Free substation checkContact
Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.
No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.
✓ Received. We will email you within one business day.
Or email info@benzene-group.com