Sample data centre power brief

A 100 MW data centre: Blyth, Ratcliffe-on-Soar or Didcot?

A worked example of our data centre power brief, built from real public data. There is no client. We picked three areas near transmission substations as examples of different kinds of location; nothing here says a data centre is planned at any of them. A real brief compares up to three sites of your choosing and arrives within seven working days.

20 November 2026 · Prepared by Benzene as a sample · A desk review of public registers and published network data. Not legal advice, an engineering study or a connection offer.

1. The short answer

  • Blyth. The busiest node of the three: 3,650 MW queued across 4 projects, all offshore wind or storage, dated 2029 to 2036. It also has the most generation queuing nearby, which matters if you want to talk about co-location or a private wire. Confirmed figures, Inferred reading.
  • Ratcliffe-on-Soar. The least crowded: 909.9 MW queued across 4 projects, dated 2028 to 2033, on a former coal station site that already has 225 MW of storage and gas turbines connected. Confirmed figures, Inferred reading.
  • Didcot. 1,579 MW connected and 1,179.9 MW queued across 6 entries, dated 2027 to 2037. The only one of the three with a Gate 2 project (300 MW). The nearest local substations are rated Red for new demand, apart from two 132 kV primaries. Confirmed

None of this says whether 100 MW of demand can connect at any of them. NESO's register lists generation and storage, not demand applications. That is a question for NESO and the network operator, and section 6 lists what to ask. Inferred

Request modelledA 100 MW data centre, comparing three candidate areas
ClientNone: sample only
Register data as ofNESO TEC Register file of 16 November 2026
Local network data as ofNorthern Powergrid, last processed 27 July 2026; SSEN Distribution, March 2026. National Grid Electricity Distribution not yet covered.

2. The transmission substations

AreaRegister rowsConnected MWQueued MWQueued MW by GateContracted dates (queued)
Blyth, Northumberland53963,650Gate 1: 1,850
No Gate shown: 1,800
Nov 2029 to Oct 2036
Ratcliffe-on-Soar, Nottinghamshire7266.76909.9Gate 1: 639.9
No Gate shown: 270
Oct 2028 to Oct 2033
Didcot, Oxfordshire81,5791,179.9Gate 2: 300
Gate 1: 429.9
No Gate shown: 450
Mar 2027 to Oct 2037

Confirmed from the NESO TEC Register of 16 November 2026. The counts and sums are ours, over every row whose connection site name contains the area name. "Queued" is the MW increase not yet connected.

Blyth

ProjectMWTechnologyGateContracted dateRegister status
Berwick Bank Offshore Wind Farm CBlyth 400kV Substation1,800 queuedOffshore windNot shown30 November 2029Scoping
Icewind BlythBlyth 400kV Substation1,000 queuedOffshore windGate 131 October 2031Scoping
Blyth BESSBlyth 275kV Substation450 queuedStorageGate 131 October 2036Scoping
Hope Battery StorageBlyth 400kV Substation400 queuedStorageGate 131 October 2036Scoping
Lynemouth Power StationBlyth GSP396 connectedBiomassBuilt

Ratcliffe-on-Soar

ProjectMWTechnologyGateContracted dateRegister status
Whatton EstateRatcliffe GSP130 queuedStorage, SolarNot shown30 October 2028Scoping
EMERGE CentreRatcliffe-on-Soar 132kV Substation49.9 queuedWasteGate 129 June 2029Scoping
Ratcliffe Kegworth Road BEGARatcliffe-on-Soar 132kV Substation140 queuedStorage, SolarNot shown30 October 2033Scoping
Ratcliffe-on-Soar IIRatcliffe-on-Soar 400kV Substation590 queuedStorage, SolarGate 130 October 2033Scoping
Ratcliffe on SoarRatcliffe-on-Soar 400kV Substation225 connectedStorage, Gas turbine (OCGT)Built
Redfield Road ARatcliffe GSP20.88 connectedCHPBuilt
Redfield Road BRatcliffe GSP20.88 connectedThermalBuilt

Didcot

ProjectMWTechnologyGateContracted dateRegister status
Didcot BatteryDidcot 400/132kV Substation100 queuedDemand, StorageGate 131 March 2027Scoping
Didcot Energy ParkDidcot 400kV Substation300 queuedStorageNot shown31 October 2027Awaiting Consents
Didcot RoadDidcot 400kV Substation300 queuedStorageGate 231 October 2028Consents Approved
Didcot BDidcot 400kV Substation230 queued (plus 1,475 connected)Gas (CCGT), StorageGate 131 October 2037Built
Didcot BESS 2Didcot 132kV GIS Substation99.9 queuedStorageGate 131 October 2037Scoping
Sutton CourtenayDidcot 132kV Substation150 queuedDemand, StorageNot shown31 October 2037Scoping
Didcot A GTsDidcot 400kV Substation100 connectedGas turbine (OCGT)Built
PeakGen BEGA - DidcotDidcot GSP4 connectedOil and gas turbineBuilt

All rows Confirmed from the NESO TEC Register of 16 November 2026, names as the register shows them. Two Didcot storage rows list "Demand" in their plant type; that is battery import, not a data centre. No changes at any of the three areas between the registers of 13 and 16 November.

3. The local network

Blyth (Northern Powergrid)

SubstationTypeDistanceGeneration headroom MWRatingDemand headroom MWRating
BlythGrid supply point, 132 kVAt the GSP0.0Amber45.8Amber
BlythGrid supply point, 66 kVAt the GSP0.0Green0.0Green
Maddison StreetPrimary, 11 kV1.7 km0.0Green0.0Green
WansbeckPrimary, 11 kV2.1 km0.0Amber0.0Amber
ReservoirPrimary, 20 kV4.2 km0.0Amber0.0Green
AshingtonPrimary, 11 kV4.3 km0.0Red0.0Amber

Northern Powergrid, Heat map data, last processed 27 July 2026, read 19 November 2026, shown as published. Distances are straight-line and approximate.

Didcot (SSEN Distribution)

SubstationTypeDistanceGeneration headroom MWRatingDemand headroom MVARating
MiltonPrimary, 33 kV0.9 km0.0Red0.0Red
DraytonBulk supply point, 132 kV4.3 km0.0Red0.0Red
FulscotPrimary, 33 kV4.3 km0.0Red0.0Red
CulhamPrimary, 132 kV4.8 km0.0Red15.5Green
Winsmore LanePrimary, 33 kV5.3 km0.0Red0.0Red
HarwellPrimary, 132 kV6.0 km0.0Red39.1Green

SSEN Distribution, Headroom Dashboard Data, March 2026, read 19 November 2026, shown as published. Distances are straight-line and approximate.

Ratcliffe-on-Soar (National Grid Electricity Distribution)

Not yet covered. We have asked National Grid Electricity Distribution to confirm the licence terms for its headroom data before we show it. A real brief would say the same, or quote the operator's own map with its date.

What this means. Local substations near Blyth and Didcot show tens of MW of demand headroom at most, and often none. 100 MW is a transmission-scale request: the local network is a guide to how tight the area is, not a route to connection. Inferred

Confirmed from each operator's published data, shown as published, with the operator's caveats. Northern Powergrid: Supported by Northern Powergrid Open Data. SSEN: Contains SSEN Distribution data, CC BY 4.0; SSEN gives demand headroom in MVA. Operators work out headroom their own way, so compare within an area rather than across them.

4. Generation nearby

This sample lists only projects on the same substations and grid supply points (section 2). A real brief adds register projects within about 10 km, for co-location or private wire conversations.

5. The rules that apply

  • Ofgem's proposed Data Centre Commitment Fee. £237,500 to £712,500 per MW, for projects above 40 MW on the transmission system, and above 40 MW on the distribution system where a Transmission Entry Assessment applies. Held from offer acceptance to energisation, returned if the project proceeds as planned and forfeited if it terminates or fails the requirements. Confirmed Ofgem, Curate consultation, 29 July 2026, paragraphs 4.1, 5.1 and 5.3. A proposal: the consultation closed on 16 September 2026 and Ofgem said it intends to decide later in 2026. We had not found a decision by 20 November 2026.
  • At 100 MW that would be £23.75m to £71.25m, the same at all three areas. Inferred 100 × £237,500 and 100 × £712,500.
  • The Data Centre Covenant. HM Treasury's policy paper of 28 October 2026 sets five tests. For "strategic" data centres that meet them, the government offers to reserve and reallocate grid connections, identify additional capacity and accelerate connections before 2030. "Strategic data centre" is not yet defined and no MW threshold is given. Confirmed GOV.UK, The Data Centre Covenant.

6. Questions to put to NESO and the network operator

  1. Is there a demand connection point at this substation for 100 MW, and at what voltage?
  2. What demand is already contracted or applied for at this node? The register will not tell us.
  3. What reinforcement works are needed, and what are their planned dates?
  4. Would a non-firm or flexible connection be offered earlier than a firm one?
  5. Would the 40 MW fee threshold apply to the project as one application, or stage by stage?

7. Comparison

BlythRatcliffe-on-SoarDidcot
Queued MW at node Confirmed3,650909.91,179.9
Gate 2 MW queued Confirmed00300
Latest queued date ConfirmedOct 2036Oct 2033Oct 2037
Connected at node Confirmed396 MW266.76 MW1,579 MW
Best local demand headroom nearby Confirmed45.8 MW (Blyth 132 kV GSP, Amber)Not yet covered39.1 MVA (Harwell, Green)
Fee at 100 MW, if adopted Inferred£23.75m to £71.25mSameSame

8. Sources and limits

SourceUsed for
NESO TEC Register, file of 16 November 2026Sections 1, 2 and 7
Northern Powergrid heat map data, last processed 27 July 2026Section 3, Blyth
SSEN Distribution, Headroom Dashboard Data, March 2026Section 3, Didcot
Ofgem, Curate: Demand Connections Reform consultation, 29 July 2026Section 5, fee
HM Treasury, The Data Centre Covenant, 28 October 2026Section 5, Covenant

Confirmed read on a primary source. Reported taken from a named source we have not checked against the original. Inferred our reading of confirmed facts. The register lists generation and storage, not demand, and we have seen no demand offer at these sites. We do not forecast connection dates. Registers change, so findings are correct only as of the dates shown. Not legal advice or an engineering study.

Weighing real sites? A data centre power brief costs £2,950 for up to three sites, or £1,950 for one, and takes seven working days. Or start with a free check: tell us the nearest substation and we will send you what is queued there.

Free substation check

Contact

Name a substation. We will send you its queue, free.

Tell us a substation, a site or a postcode. Within one business day we will email you what is queued there: how much capacity, which Gates and what dates. No charge and no obligation.

No mailing lists. A person will reply. Want to talk about something else? Leave the first box blank.

✓ Received. We will email you within one business day.

Or email info@benzene-group.com